SIAM J. Comput. 23, pp. 662-669 (8 pages)
A New Insight into the Coffman–Graham Algorithm
The approximate solution of the $m$-machine problem is addressed. The Lam–Sethi worst-case analysis of the Coffman–Graham algorithm is set up to be partly incorrect. A slightly different context is set up to correct and complete this analysis. It is shown that the makespan of a schedule computed by an extended Coffman–Graham algorithm is lower than or at worst equal to $({{2 - 2} / m})\omega _{{\text{opt}}} - {{(m - 3)} / m}$, where $\omega _{{\text{opt}}} $ is the minimal makespan of a schedule.